Client    Local Government Engineering Department (LGED) & Asian Infrastructure Investment Bank

 

Description of work: 

 

Under this project, Waste Concern Consultants provided following services:

  • Prepared Pre-feasibility Reports for USD 500 million; Policy Briefs on SWM ; subproject selection criteria for ISWMIP; identification of Best Practicable Options (BPOs) in SWM for collection, transportation, processing and disposal; Sub-project identification screening, preparation of ISWMIP framework documents.
  • Prepared Draft Feasibility Reports for each sub-project for USD 150 million (i): Conducting of local stakeholder analysis and consultation process, preparation of institutional strengthening plan, capacity assessment for the entire solid waste management chain and municipal waste management plans.
  • Prepared Final Feasibility Reports.
  • Prepared Draft Detailed Engineering Designs (DEDs) for USD 50 million. Preparing and delivering draft covering Part-B (3) containing DEDs and costs to PMCU of ISWMIP and AIIB.
  • Prepared Final DEDs: Preparation and delivery final DEDs and preparation of procurement plan
  • Prepared ESIA, ESMF, RPF, & Livelihood Restoration Plan
  • Prepared Bid Documents, Procurement Plan, Project Administration Manual and Project Financial Manual

 

Location:   Bangladesh (3 City Corporation and 23 Municipalities)

Period:    March 2022 to June 2023

 

Integrated Solid Waste Management Improvement Project (ISWMIP) supported by the Asian Infrastructure Investment Bank (AIIB) and implemented by the Local Government Engineering Department (LGED)

Aerial View of the Proposed Site and Proposed ILF&RRF in Rajshahi City Corporation Area